JTRS was commissioned to replace two 25-ton split ducted systems that served a section of this building with a 600,000 BTU/hr or 50-ton Trane VRF system that serves two (2) 25-ton Solution Plus Air Handling Units (AHU’s). This type of system allows us to connect air handling units up to a capacity of 80HP. 
 
The building owner had strict operating times that only allowed for work to be done during weekends. Through the collaborative efforts of our mechanical team, we successfully dismantled the interior ceilings, air handlers, associated ductwork, and installed the two new 25 Ton air handlers,  four (4) VRF condensing units, new ductwork and acoustic ceilings in 2-1/2 days.